| Phase | Task | Duration | Type |
|---|---|---|---|
| Requirements | Define user outcomes | 2 days | Task |
| Requirements | Document functional requirements | 3 days | Task |
| Requirements | Agree acceptance criteria | — | Milestone |
| Architecture | Choose the technical approach | 3 days | Task |
| Architecture | Model data and interfaces | 3 days | Task |
| Architecture | Review security and privacy | 2 days | Task |
| Implementation | Set up development environments | 2 days | Task |
| Implementation | Build the core workflow | 8 days | Task |
| Implementation | Add validation and error states | 3 days | Task |
| Integration | Connect external services | 4 days | Task |
| Integration | Prepare representative test data | 2 days | Task |
| Integration | Complete integration checks | 3 days | Task |
| QA and UAT | Run automated tests | 3 days | Task |
| QA and UAT | Complete accessibility checks | 2 days | Task |
| QA and UAT | Obtain user acceptance | — | Milestone |
| Deployment | Prepare release and rollback steps | 2 days | Task |
| Deployment | Deploy to production | 1 days | Task |
| Deployment | Complete production smoke test | 1 days | Task |
The plan moves through requirements, architecture, implementation, integration, qa and uat, deployment. Durations are working-day estimates and dependencies keep downstream dates aligned.
Turn uncertain requirements into examples and acceptance checks.
Request credentials and test environments during architecture.
Use a release checklist and rehearse rollback.
This preset is a starting point, not professional advice. It was last reviewed on . See how schedules are calculated.